The Schwinge Bridge is a section of the detour around the city of Stade.An opening of 15 m width has to be provided to ensure the accessibility to the ships on the river Schwinge.
1985 - 1988
Civil Egineering Structures Infrastructure
bridges, roads and highways, bewegliche bridges
study, project design, structural design, on-site construction inspection
6,500,000 EUR
In European cooperation the Deutsches Elektronen-Synchrotron DESY plans the construction of an X-ray laser. The plant is designed to produce high-intense ultra-short X-ray flashes with the characteristics of laser-light for scientific purposes.
2004 - 2012
Civil Egineering Structures
Universität / Institut, tunnles
study, official approval of planning, project design, structural design, site management, on-site construction inspection, supervision of health and safety protection
970,000,000 EUR
In order to extend the HHLA Container Terminal Tollerort in the Port of Hamburg another 300 m of quay wall were built. In addition the “Europakai” was extended by 50 m and in connection with this land with an area of approximately 40.000 m² claimed.
1997 - 2000
Civil Egineering Structures Industrial and Commercial Buildings Infrastructure
trade centres, flood protection structures, warehouses, storage facilities for water pollutants
study, general construction planning, project management, project design, structural design, site management, on-site construction inspection
12,500,000 EUR
A new Highway bridge is planned to substitute the removed railway crossing of Dassauweg in Hamburg. The construction site is situated in the natural conservation area.
2001 - 2003
Civil Egineering Structures Infrastructure
bridges, railway structures, roads and highways
project design, structural design
4,200,000 EUR
In order to make the new areas of the HafenCity accessible to fire protection and first aid services, there is a need for a new network of pathways at 7.5 m above sea level (SL). The Kibbelsteg bridges connect this network to the high tide protected areas of the inner city, crossing the Zollkanal, the Brooksfleet, and the “Am Sandtorkai“ street.
1999 - 2002
Civil Egineering Structures Infrastructure
bridges, roads and highways
study, general construction planning, project design, analysis of existing structures, structural design, on-site construction inspection, feasibility study
5,300,000 EUR
The new footbridge at the Buchholz Train Station will serve as a connection between the two city areas, which are separated by the railway track. Furthermore, new staircases and elevators will provide access to the northern and southern platforms.
2003 - 2005
Civil Egineering Structures Infrastructure
bridges
project design, structural design, on-site construction inspection, Site supervision as accredited Check Engineer, supervision of health and safety protection
2,700,000 EUR
The construction of the “Klimahaus“ (Climate House) in the area between the old harbour of Bremerhaven and the river Weser will create a special tourist attraction for Bremerhaven.
2003 - 2007
Civil Egineering Structures Infrastructure
bridges, bewegliche bridges
general construction planning, project design, analysis of existing structures, structural design, site management, on-site construction inspection, supervision of health and safety protection
4,500,000 EUR
The TESLA Test Facility (TTF) is an experimental plant with the purpose to test the operation of the linear accelerator (LC) and the X-ray laser (XFEL) for the planned 33 km long TeV Energy Superconducting Linear Accelerator (TESLA).
1995 - 2000
Civil Egineering Structures
Universität / Institut, tunnles
project design, structural design, on-site construction inspection
1,700,000 EUR
The waste water treatment plant in Lübeck has set a long-term plan to decontaminate the discharge system and to convert the central treatment pools of the existing mixed water canalisation to a divided canalisation system. In achieving this goal, the treatment plant requires the construction of two new underground collection channels.
2001 - 2003
Civil Egineering Structures
tunnles, sluice
project design
5,000,000 EUR